Task: Screw an M8 hex bolt with washer into a tapped hole, using a combination wrench.
| Element | Table time | |---------|-------------| | Pick up bolt | 0.25 min | | Pick up washer | 0.20 min | | Place washer on bolt | 0.15 min | | Position bolt in hole | 0.30 min | | Screw in 4 turns by hand | 0.40 min | | Pick up wrench | 0.25 min | | Tighten 2 turns with wrench | 0.50 min | | Lay down wrench | 0.15 min | TABEL MONTAGE TIJDEN CONFORM GUSTAV ENDE
Basic time sum = 2.20 min
Add 15% allowance (fatigue + personal) = 2.53 min standard time Task: Screw an M8 hex bolt with washer
Small workshops, repair shops, and assembly lines in developing economies often lack MTM software licenses. A printed Gustav Ende table (or a modernized version) provides 80% of the benefit at near-zero cost. Small workshops, repair shops, and assembly lines in
De tabel "Montage Tijden conform Gustav Ende" is bedoeld om uniforme normen te bieden voor de benodigde montagetijd van onderdelen en assemblages in productieomgevingen. Deze richtlijn is gebaseerd op de werkmethoden en tijdstudieprincipes van Gustav Ende en streeft naar consistente, reproduceerbare tijdsmetingen die gebruikt kunnen worden voor planning, kostencalculatie en capaciteitsberekening.